{"company_name":"Northbridge Systems","project_name":"CRM Platform Rollout","report_number":"SR-14","report_period":"Week of October 12, 2026","project_manager":"Rebecca Tan","sponsor":"Michael Oduya, VP of Sales","currency":"USD","status_summary":"The rollout is two weeks behind plan because of delayed data cleanup. The launch date holds if the data is signed off by October 30.","planned":66,"budget":"480,000.00","spent":"318,400.00","forecast":"492,000.00","target_date":"December 11, 2026","next_milestone":"Data migration sign-off","next_milestone_date":"October 30, 2026","executive_summary":"Configuration and integrations are complete and user training began for the first two regional teams. The main risk is data quality: duplicate accounts in the legacy system are taking longer to resolve than planned. Spend is slightly ahead of plan, and the forecast is 2.5% over budget, mostly from extra cleanup effort.","health":[{"area":"Schedule","status":"At risk","comment":"Data migration is two weeks late. Training and launch dates are unchanged for now.","is_green":false,"is_amber":true,"is_red":false},{"area":"Budget","status":"On track","comment":"Forecast is 2.5% over the approved budget, within the 5% tolerance.","is_green":true,"is_amber":false,"is_red":false},{"area":"Scope","status":"On track","comment":"No approved changes this period. One request is under review.","is_green":true,"is_amber":false,"is_red":false},{"area":"Quality","status":"On track","comment":"User acceptance tests passed for sales and support workflows.","is_green":true,"is_amber":false,"is_red":false}],"workstreams":[{"name":"Configuration","bar":"■■■■■■■■■■","bar_rest":"","percent":"100%","lead":"Aisha Khan"},{"name":"Integrations","bar":"■■■■■■■■■","bar_rest":"□","percent":"90%","lead":"Tomás Rivera"},{"name":"Data migration","bar":"■■■■■■","bar_rest":"□□□□","percent":"55%","lead":"Priya Shah"},{"name":"Training","bar":"■■■■","bar_rest":"□□□□□□","percent":"40%","lead":"Daniel Brooks"},{"name":"Launch preparation","bar":"■■","bar_rest":"□□□□□□□□","percent":"15%","lead":"Rebecca Tan"}],"accomplishments":["Finished all integrations with the billing and support systems","Passed user acceptance testing for sales and support workflows","Trained 34 users in the East and Central teams","Removed 4,100 duplicate accounts from the legacy data"],"next_steps":["Clean up the remaining 2,300 duplicate accounts","Run the second test migration and reconcile the results","Train the West and Enterprise teams","Confirm the go-live checklist with IT"],"milestones":[{"milestone":"Configuration complete","due":"September 18, 2026","status":"Done","note":"Completed on time","is_green":true,"is_amber":false,"is_red":false},{"milestone":"Integrations complete","due":"October 9, 2026","status":"Done","note":"Completed one day late","is_green":true,"is_amber":false,"is_red":false},{"milestone":"Data migration sign-off","due":"October 30, 2026","status":"At risk","note":"Depends on data cleanup","is_green":false,"is_amber":true,"is_red":false},{"milestone":"Training complete","due":"November 20, 2026","status":"On track","note":"Four of six teams remaining","is_green":true,"is_amber":false,"is_red":false},{"milestone":"Go-live","due":"December 11, 2026","status":"On track","note":"Holds if sign-off is met","is_green":true,"is_amber":false,"is_red":false}],"risks":[{"risk":"Duplicate accounts delay data migration sign-off","impact":"High","owner":"Priya Shah","mitigation":"Added two analysts to the cleanup and agreed a daily progress check"},{"risk":"Sales team availability for training in the last weeks of the quarter","impact":"Medium","owner":"Daniel Brooks","mitigation":"Offer evening and recorded sessions"},{"risk":"Late change to the quoting integration","impact":"Low","owner":"Tomás Rivera","mitigation":"Hold until after launch unless approved by the steering group"}],"decisions":["Approve up to $12,000 of extra budget for the data cleanup analysts","Confirm whether the quoting change request can wait until after launch"],"status_green":false,"status_amber":true,"status_red":false,"percent_complete":"62%","percent_planned":"66%","budget_used_percent":"66%","variance":"-12,000.00","days_remaining":"56","has_decisions":true}